What should I know before building in Bastrop County?

Water, wastewater, access, power and fire - the five things that decide whether a piece of land is buildable.

Whether land can be built on, and what it will cost, is usually settled by five questions. Ask them before you buy, not after.

  1. Water. Is there a utility line at the road, or does this need a well? A well is a real cost and a real timeline, and depth varies across the county.
  2. Wastewater. Sewer, or septic? Septic needs a soil evaluation, and the soil decides which system type is permitted — which changes the cost substantially.
  3. Access. Is there legal, recorded access to a public road, not just a track somebody has always used? This is the one that most often turns into a lawyer's problem.
  4. Power. How far is the nearest service, and who pays to extend it? Distance to the pole is a line item people routinely forget.
  5. Fire. Where is the nearest station, what is the water supply for firefighting, and what does that do to an insurance quote?

Inside a city versus outside

Building inside Bastrop, Elgin or Smithville city limits means city permits and city inspections. Outside them, the rules are different and generally lighter — which people hear as "easier" when it often means "the responsibility is yours". Either way, the authority on what is required is the city or the county, and they are the ones to ask.

This is an orientation, not a permit checklist. Requirements change, they differ inside and outside city limits, and the office that issues the permit is the only reliable source for what it wants today.

Terms on this page

Percolation test
A soil test determining how quickly ground absorbs water; it decides which septic system is permitted.
Legal access
A recorded right to reach a property from a public road, as opposed to informal or historic use.
Setback
The minimum distance a structure must sit from a property line or road.